WORK AREA “A”- Science & Engineering Courtyard (North)

  • Thursday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50 p.m.
  • Thursday: Excavate area adjacent to temporary sheeting (North Side)
  • Friday: Ground Breaking Ceremony/ Alumni Weekend -NO WORK SCHEDULED
  • Monday: Continue concrete removal on existing columns (North side of S&E)- NOISE IMPACT, work scheduled to STOP by 1:50 p.m.
  • Monday: Anticipate Remove existing waterproofing from foundations “NEW EDITION”; work start dependent variance/ Potential minor vibration & noise
  • Tuesday: Anticipate Remove existing waterproofing from foundations “NEW EDITION”; Potential minor vibration & noise
  • Wednesday: Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise WORK AREA “B”- South side of Science & Engineering

WORK AREA “B”- South side of Science & Engineering

  • Thursday; Excavate Foundations SE corner S&E (Lines E-C/00-01)- Truck traffic, flag-persons provided
  • Thursday; Place temporary asphalt walks- Potential minor odor/ Sidewalk closure
  • Thursday; Clean-Up surrounding area- Sidewalk closed
  • Friday; Ground Breaking Ceremony/Alumni Weekend -NO WORK SCHEDULED
  • Monday; Water Line Relocation- Relocate students/faculty to new asphalt walkway during operations
  • Tuesday; Water Line Relocation- Relocate students/faculty to new asphalt walkway during operations
  • Tuesday; Begin Form-work Installation/ Foundations Line E-C/00-01- Truck Traffic, Flag-persons provided
  • Wednesday; Water Line Relocation- Relocate students/faculty to new asphalt walkway during operations
  • Wednesday; Form-work Installation/ Foundations Line E-C/00-01- Truck Traffic, Flag-persons provided

WORK AREA “C”- Alexander lane

  • Thursday- Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7 a.m.- 3 p.m.