WORK AREA “A”- Science and Engineering Courtyard (North)/ Existing Building

  • Monday: Foundation excavation and backfill new addition Vibration and noise expected, Spotters provided.
  • Monday: MEP utility relocation in existing SandE
  • Monday: Tentative Prep for Removal of existing brick/CMU fascia on current Science and Engineering Building “Afternoon Shift (12:00 p.m. – 8:00 p.m.)
  • Monday: Make-safe utilities in Room 205A
  • Monday: Relocate generator exhaust in Peschel Courtyard
  • Tuesday: Layout of underground plumbing and electric new addition
  • Tuesday: Foundation excavation and backfill new addition Vibration and noise expected, Spotters provided.
  • Tuesday: Tentative Removal of existing brick/CMU fascia on current Science and Engineering Building “Afternoon Shift (12:00 p.m. – 8:00 p.m.)
  • Tuesday: Remove counter tops in Room 205B
  • Tuesday: Remove Form Work from concrete pour in Courtyard
  • Wednesday: Foundation excavation and backfill new addition Vibration and noise expected, Spotters provided.
  • Wednesday: Layout of underground plumbing and electric new addition
  • Wednesday: Tentative Removal of existing brick/CMU fascia on current Science and Engineering Building “Afternoon Shift (12:00 p.m. – 8:00 p.m.)
  • Wednesday: Delivery of Shoring Equipment in Courtyard new addition Spotters provided.
  • Wednesday: Temp. Wall construction in existing SandE Building
  • Thursday: Foundation excavation and backfill new addition Vibration and noise expected, Spotters provided.
  • Thursday: Layout of underground plumbing and electric “New Addition
  • Thursday: Tentative Removal of existing brick/CMU fascia on current Science and Engineering Building “Afternoon Shift (12:00 p.m. – 8:00 p.m.)
  • Thursday: Temp. Wall construction in existing SandE Building
  • Friday: Foundation excavation and backfill new addition Vibration and noise expected, Spotters provided.
  • Friday: Tentative Removal of existing brick/CMU fascia on current Science and Engineering Building “Afternoon Shift (12:00 p.m. – 8:00 p.m.)
  • Friday: Temp. Wall construction in existing SandE Building
  • Friday: Layout of underground plumbing and electric new addition

WORK AREA “B”- South side of Science and Engineering

  • Monday: Possible Placement of concrete for wall
  • Tuesday: Possible Placement of concrete for wall
  • Wednesday: Possible Removal of Form Work
  • Thursday: Possible Removal of Form Work