August 21 – August 25, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Foundation excavation & backfill new addition Vibration noise expected, Spotters provided
  • Monday: Install form-work & reinforcing steel for foundation walls/ footings
  • Monday: Install elevated form-work for L1 concrete
  • Monday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Tuesday: Install form-work & reinforcing steel for foundation walls/ footings
  • Tuesday: Foundation excavation & backfill new addition Vibration & noise expected, Spotters provided
  • Tuesday: Install elevated form-work for L1 concrete
  • Tuesday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Tuesday: Foundation Shoring Vibration & noise expected, Spotters provided
  • Wednesday: Place concrete new addition
  • Wednesday: Foundation backfill new addition Vibration & noise expected, Spotters provided
  • Wednesday: Install elevated form-work for L1 concrete
  • Wednesday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Wednesday: Foundation Shoring Vibration & noise expected, Spotters provided
  • Thursday: Install form-work & reinforcing steel for foundation walls/ footings
  • Thursday: Install Sleeves/Rebar elevated slab L1
  • Thursday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Thursday: Foundation Shoring Vibration noise expected, Spotters provided
  • Friday: Install Sleeves/Rebar elevated slab L1
  • Friday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Friday: Foundation Shoring vibration and noise expected, Spotters provided

WORK AREA “B”- South side of Science & Engineering

  • Monday; Backfill SOG-Truck Traffic, minor noise, flag-persons provided
  • Tuesday; Install underground electric
  • Wednesday; Prep for SOG- Spotters provided for truck deliveries
  • Thursday; Prep for SOG- Spotters provided for truck deliveries
  • Friday; Place SOG Spotters provided for truck deliveries

Interior Building Work:

  • Monday through Wednesday-Construct temp wall S205b
  • Thursday Through Friday- Construct temporary enclosure S006
  • Monday through Friday- Install conduit Alumni Gym
  • Temporary wall work on Level 3 (S301) Monday-Tuesday