January 22 – January 26, 2018

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: MEP Rough in Basement level
  • Monday: Apply Spray on fireproofing in basement (Level 1 East)
  • Monday: Install metal stud wall frame (Level 1)
  • Monday: MEP rough In Level 1
  • Monday: Install temporary enclosures level 3 (Existing S&E)
  • Monday: Prep Level 3 West deck for concrete placement
  • Monday: Installation of curtain wall clips
  • Tuesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Install temporary enclosures level 3 (Existing S&E)
  • Tuesday: Prep Level 3 West deck for concrete placement
  • Tuesday: installation of CMU walls (basement new addition)
  • Tuesday: MEP rough in Basement of new addition
  • Tuesday: Apply SOFP level 1 East new addition
  • Tuesday: Install metal stud wall frame (Level 1)
  • Tuesday: MEP rough In Level 1
  • Tuesday: Installation of curtain wall clips
  • Wednesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Prep Level 3 East deck for concrete placement
  • Wednesday: Complete SOFP on level 1- MILESTONE
  • Wednesday: MEP rough in Basement of new addition
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: Install metal stud wall frame (Level 1)
  • Wednesday: MEP rough In Level 1
  • Wednesday: Install temporary building enclosure Level 4
  • Wednesday: Installation of curtain wall clips
  • Thursday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: Prep Level 3 East deck for concrete placement
  • Thursday: MEP rough In Level 1
  • Thursday: MEP rough in Basement of new addition
  • Thursday: Installation of CMU walls (basement new addition)
  • Thursday: Apply SOFP level 2 West steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in Basement of new addition
  • Friday: Apply SOFP level 2 WEST steel beams
  • Friday: Prep level 3 SOD & level 2 (7-Line) placement- MILESTONE

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Selective demolition & removals Level 1 through Level 3
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE