February 5 through February 9, 2018

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: MEP Rough in Basement & level 1
  • Monday: Apply SOFP Level 2
  • Monday: layout metal stud wall frame (Level 1 East)
  • Monday: Install temporary enclosures level 4 (Existing S&E)
  • Monday: Install storm lines on Level 2
  • Monday: Install MEP sleeves/Hangers on Level 4
  • Monday: Installation of curtain wall clips
  • Monday: Installation of exterior wall clips
  • Tuesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Install temporary enclosures level 4(Existing S&E)
  • Tuesday: Install storm lines on Level 2
  • Tuesday: Installation of CMU walls (basement new addition)
  • Tuesday: MEP rough in Basement & level 1
  • Tuesday: Start Apply SOFP level 2
  • Tuesday: Layout metal stud wall frame (Level 1East)
  • Tuesday: Installation of curtain wall clips
  • Tuesday: Complete MEP sleeves/Hangers on Level 4
  • Wednesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Complete Rebar Level 4
  • Wednesday: Apply SOFP on level 2 East
  • Wednesday: MEP rough in Basement & Level 1
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: Complete temporary building enclosure Level 4
  • Wednesday: Installation of curtain wall clips
  • Wednesday: Install MEP sleeves on Level 4
  • Thursday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: Prep for concrete placement Level 4 Roof
  • Thursday: MEP rough In Basement & Level 1
  • Thursday: Installation of CMU walls (basement new addition)
  • Thursday: Complete SOFP level 2 – MILESTONE
  • Thursday: Start level 2 MEP Rough in (WEST)
  • Thursday: Installation of exterior wall clips
  • Friday: Complete installation of CMU walls (basement new addition)- MILESTONE
  • Friday: MEP rough in Basement, Level 1, & Level 2
  • Friday: Apply SOFP level 3 WEST & EAST steel beams
  • Friday: Level 4 (LOW ROOF) Concrete placement- MILESTONE
  • Friday: Installation of curtain wall clips
  • Friday: Installation of exterior wall clips

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Selective demolition & removals Level 1 through Level 3
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE