September 18 – September 22, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

    • Monday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Monday: Strip Concrete walls
    • Monday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Monday: Remove shoring under Level 1 deck
    • Tuesday: Excavate & Backfill in courtyard
    • Tuesday: Install shoring for elevated deck
    • Tuesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Tuesday: Install MEP sleeves in concrete foundation wall
    • Tuesday: Place Concrete walls/Footings; Expect truck traffic and minor noise (flag person will be present)
    • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Wednesday: Remove shoring under Level 1 deck
    • Wednesday:Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Wednesday: Install shoring for elevated deck
    • Wednesday: Install Sump Pit in courtyard
    • Wednesday: Temporarily remove exhaust stack on Existing S&E
    • Thursday: Place Concrete walls & Footings; Expect truck traffic and minor noise (flag person will be present)
    • Thursday: Install shoring for elevated deck
    • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Thursday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Friday: Install shoring for elevated deck
    • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Friday: Excavate & Backfill in courtyard Expect truck traffic and minor noise (flag person will be present)

WORK AREA “B”- South side of Science & Engineering

    • Monday: Foundation wall waterproofing
    • Tuesday: Foundation Wall waterproofing
    • Wednesday: Backfill foundation walls (SW) Expect truck traffic and minor noise (flag person will be present)
    • Thursday: Backfill foundation walls (SW) Expect truck traffic and minor noise (flag person will be present)

September 5 – September 8, 2017

View construction map [PD.F]

WORK AREA “A”- Science and Engineering Courtyard (North)/ Existing Building

  • Tuesday: Install solder pile and lagging in courtyard
  • Tuesday: Install rebar/electric conduits/Sleeves/form-work for elevated deck
  • Tuesday: Layout and Install sleeve for electrical and plumbing utilities
  • Tuesday: Selective Removals of existing Science and Engineering Building, levels 1 – 3 noise and vibration expected
  • Wednesday: Excavate and install new sewer pit
  • Wednesday: Layout and Install underground MEP
  • Wednesday: Place concrete foundations in courtyard adjacent to Bailey Hall
  • Wednesday: Install solder pile and lagging in courtyard
  • Wednesday: Saw-cut existing concrete slab in SandE basement noise and vibration expected; coordinate with class schedules”
  • Wednesday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Thursday: Place Concrete for elevated deck- (tentative; Schedule based on College coordination and weather)
  • Thursday: Layout and Install underground MEP
  • Thursday: Install solder pile and lagging in courtyard
  • Thursday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Thursday: Place Concrete for walls in new addition
  • Friday: Layout and Install sleeve for electrical and plumbing utilities
  • Friday: Install solder pile and lagging in courtyard
  • Friday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Friday: Place concrete foundations New Addition
  • Saturday: Excavation/Form-work for concrete foundations

WORK AREA “B”- South side of Science and Engineering

  • Tuesday: Install door in room S006; (coordination with college)
  • Tuesday: Backfill Expect truck traffic and minor noise (flag person will be present)
  • ALL WEEK: Area clean-up

WORK AREA “C” – Alexander Lane

  • Expect continued construction traffic (flagger and spotter provided for all deliveries)

August 21 – August 25, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Foundation excavation & backfill new addition Vibration noise expected, Spotters provided
  • Monday: Install form-work & reinforcing steel for foundation walls/ footings
  • Monday: Install elevated form-work for L1 concrete
  • Monday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Tuesday: Install form-work & reinforcing steel for foundation walls/ footings
  • Tuesday: Foundation excavation & backfill new addition Vibration & noise expected, Spotters provided
  • Tuesday: Install elevated form-work for L1 concrete
  • Tuesday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Tuesday: Foundation Shoring Vibration & noise expected, Spotters provided
  • Wednesday: Place concrete new addition
  • Wednesday: Foundation backfill new addition Vibration & noise expected, Spotters provided
  • Wednesday: Install elevated form-work for L1 concrete
  • Wednesday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Wednesday: Foundation Shoring Vibration & noise expected, Spotters provided
  • Thursday: Install form-work & reinforcing steel for foundation walls/ footings
  • Thursday: Install Sleeves/Rebar elevated slab L1
  • Thursday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Thursday: Foundation Shoring Vibration noise expected, Spotters provided
  • Friday: Install Sleeves/Rebar elevated slab L1
  • Friday: Exterior facade demolition (North side of Existing S&E) Level 1 through 3 – noise vibration expected (12:30 p.m. through 8:30 p.m.)
  • Friday: Foundation Shoring vibration and noise expected, Spotters provided

WORK AREA “B”- South side of Science & Engineering

  • Monday; Backfill SOG-Truck Traffic, minor noise, flag-persons provided
  • Tuesday; Install underground electric
  • Wednesday; Prep for SOG- Spotters provided for truck deliveries
  • Thursday; Prep for SOG- Spotters provided for truck deliveries
  • Friday; Place SOG Spotters provided for truck deliveries

Interior Building Work:

  • Monday through Wednesday-Construct temp wall S205b
  • Thursday Through Friday- Construct temporary enclosure S006
  • Monday through Friday- Install conduit Alumni Gym
  • Temporary wall work on Level 3 (S301) Monday-Tuesday