April 28 – May 5, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)

  • Friday: Remove existing concrete debris with dump truck- No potential impacts, light truck traffic on Alexander Lane
  • Monday: Establish survey points for new edition- No Impacts
  • Tuesday: Grade area and install geotextile fabric, place 6-inches of compacted sub-base- Potential minor noise/vibration/ Increased truck traffic on Alexander Lane
  • Wednesday: Continue placement of 6-inches of compacted sub-base- Potential minor noise/vibration/ Increased truck traffic on Alexander Lane

WORK AREA “B”- South side of Science & Engineering

  • Friday: No work scheduled
  • Monday: Excavate for asphalt sidewalks- Flag-persons to be provided. Student traffic detour through S&E
  • Tuesday: Place asphalt in sidewalks- Flag-persons to be provided, potential odor due to asphalt. Student traffic detour through S&E
  • Wednesday: Existing Landscape removals/ Potential condenser relocation- Student traffic re-routed onto new asphalt sidewalk/ flag-persons provided

WORK AREA “C”- Alexander Lane

  • Friday: Place asphalt in area located between temporary fence & Bailey Field- Light Truck Traffic on Alexander Lane, Flag-persons to be provided, potential odor due to asphalt.

WORK AREA “D”- Contractor Break Area

  • Friday: Complete stone placement & grading operations- NO IMPACTS
  • Monday: Install temporary fence- NO IMPACTS

WORK AREA “E”- Contractor Material Lay-down

  • Friday: Continue excavation of existing material- Continued truck traffic at intersection of Nott Street & Alexander lane
  • Monday: Complete excavation of existing material –Continued truck traffic at intersection of Nott Street & Alexander lane
  • Tuesday: Install geotextile fabric and place 6-inches compacted sub-base- Continued truck traffic at intersection of Nott Street & Alexander lane