May 4 – May 11, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)

  • Thursday: Place geotextile fabric and 6-inches of compacted sub-base/ Establish survey points for “NEW EDITION”- Potential Minor Vibration & Noise
  • Friday: Continue survey points for “NEW EDITION”; Start excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise
  • Monday: Continue excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise
  • Tuesday: Layout concrete removal on existing columns (North side of S&E)
  • Wednesday: Remove concrete from existing columns- Vibration & Noise to adjacent classrooms North side of S&E

WORK AREA “B”- South side of Science & Engineering

  • Friday: Relocate existing condenser units- Coordinate with facility IT department during operation
  • Monday: Remove existing tree (morning) & begin utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations
  • Tuesday: Continue utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations
  • Wednesday: Continue utility relocations SW corner S&E.- Relocate students/faculty to new asphalt walkway during operations

WORK AREA “C”- Alexander lane

  • Thursday through Monday; Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7 a.m.- 3 p.m.

WORK AREA “D”- Contractor break Area

  • Friday: Install temporary fence & gates

WORK AREA “E”- Contractor Material Lay-down Area

  • Thursday: Remove curb, box out & asphalt paving to widen entrance at Alexander Drive- Flag-persons provided at each portion of each portion of intersection
  • Friday: Install temporary fence