The following activities shall take place on Wednesday morning May 10 through Thursday May 11, 2017 in order begin selective exterior wall demolition on the Science & Engineering Building.
- 7:00 a.m. – Layout Areas on North elevation of Science & Engineering building.
- 7:45a.m. – Begin Saw cutting & hammering concrete away from columns
- 11:00 a.m. – Remove Brick Fascia from exterior walls (LEVEL 1) –North Elevation
- 3:00 .pm. -Clean-up
This operation shall create noise only. Surrounding areas shall be monitored throughout the operation. Additional signage shall be provided through buildings to alert Students & faculty.
Rooms adjacent to work: S105,S103,S101, & S159