WORK AREA “A”- Science and Engineering Courtyard (North)

  • Monday: Excavate foundations new addition Lines R1-R6- Increased Truck traffic during operation
  • Monday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Monday: Begin Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Monday: Mechanical, Electrical, Plumbing,  relocation between Bailey Hall and Science and Engineering
  • Tuesday: Excavate foundations  new addition Lines R1-R6- Increased Truck traffic during operation
  • Tuesday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Tuesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Tuesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Wednesday: Foundation excavation of “new addition- Increased Truck traffic during operation
  • Wednesday: Install form-work new addition; R1-R6
  • Wednesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Wednesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Wednesday: Start Temporary wall work located in room S201, S201A, S205
  • Thursday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Thursday: Install Rebar new addition; R1-R6
  • Thursday: Temporary wall work located in room S201, S201A, S205 (Level 2 SandE)

WORK AREA “B”- South side of Science and Engineering

  • Monday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
  • Tuesday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
  • Tuesday: Install additional shoring SW foundations (S-Q/ 0.00-0.9)
  • Wednesday: Place concrete for foundation walls SE corner (Lines 00-0.9/C-D)- Potential minor vibration and noise
  • Wednesday: Foundation undercut/stone install of SW corner (Lines S-Q/0-0.9)- Truck Traffic, flag persons provided
  • Thursday: Waterproofing abatement SW corner (S-Q/0-0.9) Potential minor vibration and noise
  • Remove form-work: Foundation walls SE corner (Lines 00-0.9/C-D)- Truck Traffic, flag persons provided