WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Install elevated deck form work
- Monday: Install Rebar & form-work for remaining foundation walls
- Monday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
- Monday: Selective demolition on existing roof- Expect minor noise & vibration
- Monday: Install mechanical sleeves & hangers on elevated deck
- Monday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
- Tuesday: Install elevated deck form work
- Tuesday: Place concrete fin New addition foundations-expect trucks and minor noise, flag persons shall be provided
- Tuesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
- Tuesday: Selective demolition on existing roof- Expect minor noise & vibration
- Tuesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
- Wednesday: Install elevated deck form work
- Wednesday: Remove form-work for foundation walls
- Wednesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
- Wednesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
- Thursday: Install elevated deck form work
- Thursday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
- Thursday: Install rebar for elevated deck
- Friday: Complete elevated deck form work
WORK AREA “B”- South side of Science & Engineering
- Monday- Foundation backfill
- Tuesday- Foundation backfill
- Wednesday- Existing building steel exploration- Minor noise & vibration