>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
- Monday: Strip Concrete walls
- Monday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
- Monday: Install elevated deck shoring/Rebar/Sleeves
- Tuesday: Install elevated deck shoring/Rebar/Sleeves
- Tuesday: Selective demolition on Existing S&E roof; EXPECT MINOR VIBRATION & NOISE until 1:30 p.m.
- Tuesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
- Tuesday: Install foundation wall waterproofing/Backfill
- Tuesday: Selective brick removal SW corner of S&E
- Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
- Wednesday: Install elevated deck shoring/Rebar/Sleeves
- Wednesday: Install foundation wall waterproofing/Backfill
- Wednesday: Install temporary fence between Butterfield & Steinmetz
- Thursday: Prep elevated deck for concrete placement
- Thursday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
- Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
- Thursday: Install foundation wall waterproofing/Backfill Expect truck traffic and minor noise (flag person will be present)
- Friday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
- Friday: Install new electrical manholes #7 through #9
- Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
- Friday: Install foundation wall waterproofing/Backfill ; Expect truck traffic and minor noise (flag person will be present)
WORK AREA “B”- South side of Science & Engineering
- Monday: Backfill Foundations Prep walkway for asphalt