October 9 – October 13, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Strip Concrete walls
  • Monday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Install elevated deck shoring/Rebar/Sleeves
  • Tuesday: Install elevated deck shoring/Rebar/Sleeves
  • Tuesday: Selective demolition on Existing S&E roof; EXPECT MINOR VIBRATION & NOISE until 1:30 p.m.
  • Tuesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Install foundation wall waterproofing/Backfill
  • Tuesday: Selective brick removal SW corner of S&E
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Install elevated deck shoring/Rebar/Sleeves
  • Wednesday: Install foundation wall waterproofing/Backfill
  • Wednesday: Install temporary fence between Butterfield & Steinmetz
  • Thursday: Prep elevated deck for concrete placement
  • Thursday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Install foundation wall waterproofing/Backfill Expect truck traffic and minor noise (flag person will be present)
  • Friday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
  • Friday: Install new electrical manholes #7 through #9
  • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Friday: Install foundation wall waterproofing/Backfill ; Expect truck traffic and minor noise (flag person will be present)

WORK AREA “B”- South side of Science & Engineering

  • Monday: Backfill Foundations Prep walkway for asphalt
Print Friendly, PDF & Email