>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
> Monday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
> Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
> Monday: Elevated slab shoring removal
> Monday: Establish emergency egress North side of Bailey hall & relocate fence
> Monday: Excavate & install underground utilities
> Tuesday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
> Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
> Tuesday: Excavate & Install underground utilities
> Tuesday: Install electrical manholes located between Butterfield & Steinmetz
> Wednesday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
> Wednesday: Underground utility excavation
> Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
> Thursday: Excavate & Install underground utilities
> Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
> Friday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
WORK AREA “B”- South side of Science & Engineering
> Monday: Complete all emergency egress asphalt paving & relocate temp. fence
> Tuesday: CLOSE CONNECTOR BETWEEN BAILEY HALL & S&E
> Wednesday: Selective demolition/ enabling/ temp wall installation
> Thursday: Relocation condenser units
> Thursday: Selective demolition/ enabling/ temp wall installation
> Friday: Selective demolition/ enabling/ temp wall installation
> Friday: Relocation of condenser units
Bailey Hall/ S&E re-phase work
> Monday: Remove all excess materials, clean