November 13 – November 17, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection sequence 2A (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Basement MEP excavation and installation; Expect truck traffic and minor noise
  • Monday: Installation of floor slab electric conduit
  • Tuesday: Basement MEP excavation and installation
  • Tuesday: Steel Erection sequence 2A (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Installation of floor slab electric conduit
  • Tuesday: Install electrical manholes located between Butterfield & Steinmetz
  • Wednesday: Steel Erection sequence 2A (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Basement MEP excavation and installation
  • Wednesday: Install electrical manholes located between Butterfield & Steinmetz
  • Wednesday: Basement Slab on Grade preparation
  • Wednesday: Installation of floor slab electric conduit
  • Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Basement Slab on Grade preparation
  • Thursday: Basement MEP excavation and installation
  • Friday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Basement MEP excavation and installation
  • Friday: Installation of floor slab electric conduit
  • Friday: Basement Slab on Grade preparation

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Exterior Brick & Concrete removal SW corner (Start 1pm)
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Exterior Brick & Concrete removal SW corner (Start 2pm)
  • Thursday: Exterior Brick & Concrete removal SW corner (Start 1pm)
  • Thursday: Relocation condenser units
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Relocation of condenser units
  • Friday: Exterior Brick & Concrete removal SW corner (Start 1pm); EXPECT NOISE & VIBRATION

 

Print Friendly, PDF & Email