November 20 – November 24, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Basement MEP excavation and installation; Expect truck traffic and minor noise
  • Monday: Installation of floor slab electric conduit
  • Tuesday: Basement MEP excavation and installation
  • Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Installation of floor slab electric conduit
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Basement MEP excavation and installation
  • Wednesday: Installation of floor slab electric conduit
  • Thursday: NO WORK HAPPY THANKSGIVING!
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Basement MEP excavation and installation
  • Friday: Installation of floor slab electric conduit

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Monday: Install temporary stair enclosures
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Install temporary stair enclosures
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Install temporary stair enclosures