WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Monday: Prep for SOG concrete placement
- Monday: Backfill electrical conduit & Excavate for electrical room conduit
- Monday: Install temporary asphalt walkway at Bailey hall
- Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & Noise
- Tuesday: Backfill electrical conduit & Excavate for electrical room conduit
- Tuesday: Prep for SOG concrete placement
- Tuesday: Installation of dowels for CMU walls (basement new addition)
- Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Wednesday: Backfill electrical conduit & Excavate for electrical room conduit
- Wednesday: Prep for SOG concrete placement
- Wednesday: installation of dowels for CMU walls (basement new addition)
- Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Thursday: Backfill electrical conduit & Excavate for electrical room conduit
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Monday: Install temporary stair enclosures
- Monday: Existing utility enabling
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Existing utility enabling
- Wednesday: Existing Utility Enabling
- Thursday: Existing Utility Enabling
- Friday: Existing Utility Enabling