>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Monday: Installation CMU walls (basement new addition)
- Monday: Backfill electrical conduit & Excavate for electrical room conduit
- Monday: Install mechanical Sleeves & floor boxes for level 1 deck
- Monday: Install underground duct bank between Steinmetz & Butterfield
- Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & NOISE
- Tuesday: prep for SOG concrete placement for MEP’s & Electrical rooms
- Tuesday: MEP rough in Basement of new addition
- Tuesday: Install mechanical Sleeves & floor boxes for level 1 deck
- Tuesday: Installation of CMU walls (basement new addition)
- Tuesday: Install underground duct bank between Steinmetz & Butterfield
- Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Wednesday: Place concrete SOG for the new addition (basement level)
- Wednesday: Prep level 1 deck for concrete placement
- Wednesday: installation of CMU walls (basement new addition)
- Wednesday: MEP rough in Basement of new addition
- Wednesday: Install underground duct bank between Steinmetz & Butterfield
- Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Thursday: MEP rough in Basement of new addition
- Thursday: Install underground duct bank between Steinmetz & Butterfield
- Thursday: installation of CMU walls (basement new addition)
- Thursday: Prep for Level 1 SOD concrete placement
- Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
- Friday: Level 1 SOD concrete placement
- Friday: installation of CMU walls (basement new addition)
- Friday: MEP rough in Basement of new addition
- Saturday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Existing Elevator removal
- Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Wednesday: Existing Elevator removal
- Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Thursday: Existing Elevator removal
- Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Friday: Existing Elevator removal