WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel erection and detail work (new addition); expect minor vibration and noise
  • Monday: Installation CMU walls (basement new addition)</li
  • Monday: Backfill electrical conduit & Excavate for electrical room conduit
  • Monday: Install mechanical sleeves and floor boxes for level 1 deck
  • Monday: Install underground duct bank between Steinmetz & Butterfield
  • Tuesday: Steel erection and detail work (new addition) expect minor vibration and noise
  • Tuesday: prep for SOG concrete placement for MEP’s & electrical rooms
  • Tuesday: MEP rough in basement of new addition
  • Tuesday: Install mechanical sleeves and floor boxes for level 1 deck
  • Tuesday: Installation of CMU walls (basement new addition)
  • Tuesday: Install underground duct bank between Steinmetz & Butterfield
  • Wednesday: Steel erection and detail (new addition); expect minor vibration and noise
  • Wednesday: Place concrete SOG for the new addition (basement level)
  • Wednesday: Prep level 1 deck for concrete placement
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: MEP rough in basement of new addition
  • Wednesday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: Steel erection and detail (new addition); expect minor vibration and noise
  • Thursday: MEP rough in basement of new addition
  • Thursday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: installation of CMU walls (basement new addition)
  • Thursday: Prep for level 1 SOD concrete placement
  • Friday: Steel erection and detail new addition; expect minor vibration and noise
  • Friday: level 1 SOD concrete placement
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in basement of new addition
  • Saturday: Steel erection and detail new addition; expect minor vibration and noise

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Tuesday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Tuesday: Existing elevator removal
  • Wednesday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Wednesday: Existing elevator removal
  • Thursday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Thursday: Existing Elevator removal
  • Friday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Friday: Existing elevator removal