January 8 – January 12, 2018

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: MEP Rough in Basement level
  • Monday: Apply Spray on fireproofing in basement (Level 0)
  • Monday: Install underground duct bank between Steinmetz & Butterfield
  • Monday: Backfill Generator Pad located between Steinmetz & Butterfield
  • Tuesday: Complete Steel Erection & Detail (New Addition); MILESTONE
  • Tuesday: Install temporary building enclosure Level 2
  • Tuesday: Install MEP sleeves & boxes Level 2 East
  • Tuesday: installation of CMU walls (basement new addition)
  • Tuesday: MEP rough in Basement of new addition
  • Tuesday: Grout steel column bases (Level 1)
  • Tuesday: Apply SOFP level 0 & level 1 new addition
  • Tuesday: Install underground duct bank between Steinmetz & Butterfield
  • Tuesday: Place level 0 housekeeping pads
  • Wednesday: Place Concrete underground duct bank between Steinmetz & Butterfield
  • Wednesday: Apply SOFP on level 1
  • Wednesday: MEP rough in Basement of new addition
  • Wednesday: installation of CMU walls (basement new addition)
  • Thursday: Place concrete L2 SOD West MILESTONE
  • Thursday: Prep for Level 2 EAST SOD concrete placement
  • Thursday: MEP rough in Basement of new addition
  • Thursday: Installation of CMU walls (basement new addition)
  • Thursday: Apply SOFP level 1 WEST steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in Basement of new addition
  • Friday: Apply SOFP level 1 WEST steel beams
  • Friday: Prep level 2 east SOD placement

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Selective demolition & removals Level 1 through Level 3
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Thursday: Place Concrete SOD SW IT vault- MILESTONE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE