WORK AREA “A”- Science & Engineering Courtyard (North)
- Friday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50pm
- Tuesday: Remove existing waterproofing from foundations -Potential minor vibration & noise
- Wednesday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50pm
- Wednesday: Remove existing waterproofing from foundations -Potential minor vibration & noise
- Wednesday: Install supplemental steel on Existing columns- work start dependent on paint removal/ Potential minor vibration & noise
- Wednesday: Potential Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise
- Thursday: Anticipate Remove existing waterproofing from foundations “NEW EDITION”; Potential minor vibration & noise
- Thursday: Potential Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise
- Thursday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 11:30am
WORK AREA “B”- South side of Science & Engineering
- Friday; Excavate Foundations SE corner S&E (Lines E-C/00-01)- Truck traffic, flag-persons provided
- Friday: Remove existing water line/ Backfill -Truck traffic, flag-persons provided
- Tuesday: Backfill waterline- Truck traffic, flag-persons provided
- Tuesday: Waterproofing abatement/ pipe removal SE corner foundation
- Wednesday: Complete Foundation Excavation SE corner of S&E- Sidewalk closed Relocate students/faculty to new asphalt walkway during operations
- Wednesday: Form concrete foundations- Sidewalk closed Relocate students/faculty to new asphalt walkway during operations
- Wednesday: Potential Install Temporary Sheeting for SW Corner- Potential minor vibration & noise
WORK AREA “C”- Alexander Lane
- Thursday- Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7am-3pm