WORK AREA “A”- Science and Engineering Courtyard (North)
- Monday: Excavate foundations new addition Lines R1-R6- Increased Truck traffic during operation
- Monday: Remove existing waterproofing from foundations -Potential minor vibration and noise
- Monday: Begin Temporary wall work located in Room 014 (Existing Science and Engineering)
- Monday: Mechanical, Electrical, Plumbing, relocation between Bailey Hall and Science and Engineering
- Tuesday: Excavate foundations new addition Lines R1-R6- Increased Truck traffic during operation
- Tuesday: Remove existing waterproofing from foundations -Potential minor vibration and noise
- Tuesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
- Tuesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
- Wednesday: Foundation excavation of “new addition- Increased Truck traffic during operation
- Wednesday: Install form-work new addition; R1-R6
- Wednesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
- Wednesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
- Wednesday: Start Temporary wall work located in room S201, S201A, S205
- Thursday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
- Thursday: Install Rebar new addition; R1-R6
- Thursday: Temporary wall work located in room S201, S201A, S205 (Level 2 SandE)
WORK AREA “B”- South side of Science and Engineering
- Monday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
- Tuesday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
- Tuesday: Install additional shoring SW foundations (S-Q/ 0.00-0.9)
- Wednesday: Place concrete for foundation walls SE corner (Lines 00-0.9/C-D)- Potential minor vibration and noise
- Wednesday: Foundation undercut/stone install of SW corner (Lines S-Q/0-0.9)- Truck Traffic, flag persons provided
- Thursday: Waterproofing abatement SW corner (S-Q/0-0.9) Potential minor vibration and noise
- Remove form-work: Foundation walls SE corner (Lines 00-0.9/C-D)- Truck Traffic, flag persons provided