September 25 – September 29, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install elevated deck form work
  • Monday: Install Rebar & form-work for remaining foundations
  • Monday: Excavate and backfill -expect trucks and minor noise, flag persons shall be provided
  • Monday: Install foundation waterproofing
  • Monday: Install mechanical sleeves & hangers on elevated deckv
  • Monday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Tuesday: Install elevated deck form work
  • Tuesday: Place concrete fin New addition foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Excavate and backfill -expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Install foundation waterproofing
  • Tuesday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Wednesday: Install elevated deck form work
  • Wednesday: Install form-work & rebar for foundation walls
  • Wednesday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Wednesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Thursday: Install elevated deck form work
  • Thursday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Thursday: Install form-work & rebar for foundation walls
  • Friday: Install elevated deck form work
  • Friday: Place concrete for foundations-expect trucks and minor noise, flag persons shall be provided
  • Saturday: Remove remainder of temporary sheeting

WORK AREA “B”- South side of Science & Engineering

  • Monday- Foundation Waterproofing
  • Tuesday- Foundation backfill
  • Saturday: Remove remainder of temporary sheeting