October 2, 2017 – October 6, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install elevated deck form work
  • Monday: Install Rebar & form-work for remaining foundation walls
  • Monday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Monday: Selective demolition on existing roof- Expect minor noise & vibration
  • Monday: Install mechanical sleeves & hangers on elevated deck
  • Monday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Tuesday: Install elevated deck form work
  • Tuesday: Place concrete fin New addition foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Selective demolition on existing roof- Expect minor noise & vibration
  • Tuesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Wednesday: Install elevated deck form work
  • Wednesday: Remove form-work for foundation walls
  • Wednesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Wednesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Thursday: Install elevated deck form work
  • Thursday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Thursday: Install rebar for elevated deck
  • Friday: Complete elevated deck form work

WORK AREA “B”- South side of Science & Engineering

  • Monday- Foundation backfill
  • Tuesday- Foundation backfill
  • Wednesday- Existing building steel exploration- Minor noise & vibration