October 16 – October 20, 2017

>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Install steel clips on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Install elevated deck Rebar/Sleeves/ Electrical floor boxes
  • Tuesday: Install elevated deck Rebar/Sleeves/ Electrical floor boxes
  • Tuesday: Install steel clips on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Complete elevated deck rebar & electrical boxes
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Clean & prep elevated deck for concrete placement
  • Wednesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install temporary fence between Butterfield & Steinmetz
  • Thursday: Concrete placement (TENTATIVE BASED ON WEATHER )
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Install foundation wall waterproofing/Backfill Expect truck traffic and minor noise (flag person will be present)
  • Friday: Selective demolition along 7 line; EXPECT MINOR VIBRATION & NOISE
  • Friday: Install foundation wall waterproofing/Backfill ; Expect truck traffic and minor noise (flag person will be present)
  • Friday: SURVEY anchor bolts on elevated deck Level 1

WORK AREA “B”- South side of Science & Engineering

  • Monday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Grade for new asphalt ramp
  • Thursday: Place Asphalt;Expect truck traffic and minor noise (flag person will be present)