October 23 – October 27

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install waterproofing membrane New addition foundations
  • Monday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Elevated slab shoring removal
  • Tuesday: Install waterproofing membrane New addition foundations
  • Tuesday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Elevated slab shoring removal
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Elevated Slab shoring removal
  • Wednesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Underground utility excavation
  • Thursday: Elevated slab shoring removal
  • Thursday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Underground utility excavation
  • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Friday: Underground Utility excavation
  • Friday: Elevated slab shoring removal

WORK AREA “B”- South side of Science & Engineering

  • Monday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Grade for new asphalt ramp
  • Thursday: Place Asphalt;Expect truck traffic and minor noise (flag person will be present)
  • Friday: re configure temporary fence and open entrance