December 4 – December 9, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: installation of dowels for CMU walls (basement new addition)
  • Monday: Backfill electrical conduit & Excavate for electrical room conduit
  • Monday: Excavate for underground duct bank between Steinmetz & Butterfield
  • Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill electrical conduit & Excavate for electrical room conduit
  • Tuesday: Waterproofing Abatement (Basement doors New addition)
  • Tuesday: Installation of CMU walls (basement new addition)
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Backfill electrical conduit & Excavate for electrical room conduit
  • Wednesday: Waterproofing Abatement (Basement doors New Addition)
  • Wednesday: installation of CMU walls (basement new addition)
  • Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: Backfill electrical conduit & Excavate for electrical room conduit
  • Thursday: Waterproofing Abatement (Basement doors New addition)
  • Thursday: installation of CMU walls (basement new addition)
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Backfill electrical conduit & Excavate for electrical room conduit
  • Friday: installation of CMU walls (basement new addition)
  • Friday: Waterproofing Abatement (Basement doors New addition)
  • Saturday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Monday: Existing utility enabling
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Existing utility enabling
  • Wednesday: Existing Utility Enabling
  • Thursday: Existing Utility Enabling
  • Friday: Existing Utility Enabling