December 25 – December 29

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Tuesday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION &
    NOISE
  • Tuesday: Installation CMU walls (basement new addition)
  • Tuesday: MEP Rough in Basement level
  • Tuesday: Install temporary building enclosure Level 1 & 2
  • Tuesday: Place spray-on fireproofing in basement (Level 0)
  • Tuesday: Excavate underground duct bank between Steinmetz & Butterfield
  • Tuesday: Backfill Generator Pad located between Steinmetz & Butterfield
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Install temporary building enclosure Level 1 & 2
  • Wednesday: Install MEP sleeves & boxes Level 2 East
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: MEP rough-in Basement of new addition
  • Wednesday: Install underground duct bank between Steinmetz & Butterfield
  • Wednesday: Apply SOFP on level 0
  • Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: MEP rough-in Basement of new addition
  • Thursday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: installation of CMU walls (basement new addition)
  • Thursday: Place concrete L2 SOD West
  • Thursday: Prep for Level 2 EAST SOD concrete placement
  • Thursday: Apply SOFP basement level steel beams
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Apply SOFP basement level 1 WEST steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough-in Basement of new addition

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Existing Elevator removal
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Existing Elevator removal
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Thursday: Existing Elevator removal
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Existing Elevator removal
Print Friendly, PDF & Email