WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Tuesday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION &
NOISE - Tuesday: Installation CMU walls (basement new addition)
- Tuesday: MEP Rough in Basement level
- Tuesday: Install temporary building enclosure Level 1 & 2
- Tuesday: Place spray-on fireproofing in basement (Level 0)
- Tuesday: Excavate underground duct bank between Steinmetz & Butterfield
- Tuesday: Backfill Generator Pad located between Steinmetz & Butterfield
- Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Wednesday: Install temporary building enclosure Level 1 & 2
- Wednesday: Install MEP sleeves & boxes Level 2 East
- Wednesday: installation of CMU walls (basement new addition)
- Wednesday: MEP rough-in Basement of new addition
- Wednesday: Install underground duct bank between Steinmetz & Butterfield
- Wednesday: Apply SOFP on level 0
- Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
- Thursday: MEP rough-in Basement of new addition
- Thursday: Install underground duct bank between Steinmetz & Butterfield
- Thursday: installation of CMU walls (basement new addition)
- Thursday: Place concrete L2 SOD West
- Thursday: Prep for Level 2 EAST SOD concrete placement
- Thursday: Apply SOFP basement level steel beams
- Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
- Friday: Apply SOFP basement level 1 WEST steel beams
- Friday: installation of CMU walls (basement new addition)
- Friday: MEP rough-in Basement of new addition
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Existing Elevator removal
- Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Wednesday: Existing Elevator removal
- Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Thursday: Existing Elevator removal
- Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Friday: Existing Elevator removal