>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Monday: Installation CMU walls (basement new addition)
- Monday: MEP Rough in Basement level
- Monday: Apply Spray on fireproofing in basement (Level 0)
- Monday: Install underground duct bank between Steinmetz & Butterfield
- Monday: Backfill Generator Pad located between Steinmetz & Butterfield
- Tuesday: Complete Steel Erection & Detail (New Addition); MILESTONE
- Tuesday: Install temporary building enclosure Level 2
- Tuesday: Install MEP sleeves & boxes Level 2 East
- Tuesday: installation of CMU walls (basement new addition)
- Tuesday: MEP rough in Basement of new addition
- Tuesday: Grout steel column bases (Level 1)
- Tuesday: Apply SOFP level 0 & level 1 new addition
- Tuesday: Install underground duct bank between Steinmetz & Butterfield
- Tuesday: Place level 0 housekeeping pads
- Wednesday: Place Concrete underground duct bank between Steinmetz & Butterfield
- Wednesday: Apply SOFP on level 1
- Wednesday: MEP rough in Basement of new addition
- Wednesday: installation of CMU walls (basement new addition)
- Thursday: Place concrete L2 SOD West MILESTONE
- Thursday: Prep for Level 2 EAST SOD concrete placement
- Thursday: MEP rough in Basement of new addition
- Thursday: Installation of CMU walls (basement new addition)
- Thursday: Apply SOFP level 1 WEST steel beams
- Friday: installation of CMU walls (basement new addition)
- Friday: MEP rough in Basement of new addition
- Friday: Apply SOFP level 1 WEST steel beams
- Friday: Prep level 2 east SOD placement
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Wednesday: Selective demolition & removals Level 1 through Level 3
- Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Thursday: Place Concrete SOD SW IT vault- MILESTONE
- Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE