October 16 – October 20, 2017

>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Install steel clips on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Install elevated deck Rebar/Sleeves/ Electrical floor boxes
  • Tuesday: Install elevated deck Rebar/Sleeves/ Electrical floor boxes
  • Tuesday: Install steel clips on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Complete elevated deck rebar & electrical boxes
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Clean & prep elevated deck for concrete placement
  • Wednesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install temporary fence between Butterfield & Steinmetz
  • Thursday: Concrete placement (TENTATIVE BASED ON WEATHER )
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Install foundation wall waterproofing/Backfill Expect truck traffic and minor noise (flag person will be present)
  • Friday: Selective demolition along 7 line; EXPECT MINOR VIBRATION & NOISE
  • Friday: Install foundation wall waterproofing/Backfill ; Expect truck traffic and minor noise (flag person will be present)
  • Friday: SURVEY anchor bolts on elevated deck Level 1

WORK AREA “B”- South side of Science & Engineering

  • Monday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Grade for new asphalt ramp
  • Thursday: Place Asphalt;Expect truck traffic and minor noise (flag person will be present)

October 9 – October 13, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Strip Concrete walls
  • Monday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Install elevated deck shoring/Rebar/Sleeves
  • Tuesday: Install elevated deck shoring/Rebar/Sleeves
  • Tuesday: Selective demolition on Existing S&E roof; EXPECT MINOR VIBRATION & NOISE until 1:30 p.m.
  • Tuesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Install foundation wall waterproofing/Backfill
  • Tuesday: Selective brick removal SW corner of S&E
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Install elevated deck shoring/Rebar/Sleeves
  • Wednesday: Install foundation wall waterproofing/Backfill
  • Wednesday: Install temporary fence between Butterfield & Steinmetz
  • Thursday: Prep elevated deck for concrete placement
  • Thursday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Install foundation wall waterproofing/Backfill Expect truck traffic and minor noise (flag person will be present)
  • Friday: Concrete placement (TENTATIVE BASED ON WEATHER & CONTRACTOR AVAILABILITY)
  • Friday: Install new electrical manholes #7 through #9
  • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Friday: Install foundation wall waterproofing/Backfill ; Expect truck traffic and minor noise (flag person will be present)

WORK AREA “B”- South side of Science & Engineering

  • Monday: Backfill Foundations Prep walkway for asphalt

October 2, 2017 – October 6, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install elevated deck form work
  • Monday: Install Rebar & form-work for remaining foundation walls
  • Monday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Monday: Selective demolition on existing roof- Expect minor noise & vibration
  • Monday: Install mechanical sleeves & hangers on elevated deck
  • Monday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Tuesday: Install elevated deck form work
  • Tuesday: Place concrete fin New addition foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Selective demolition on existing roof- Expect minor noise & vibration
  • Tuesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Wednesday: Install elevated deck form work
  • Wednesday: Remove form-work for foundation walls
  • Wednesday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Wednesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Thursday: Install elevated deck form work
  • Thursday: Continue installation of steel clips on existing S&E building-Minor noise & vibration
  • Thursday: Install rebar for elevated deck
  • Friday: Complete elevated deck form work

WORK AREA “B”- South side of Science & Engineering

  • Monday- Foundation backfill
  • Tuesday- Foundation backfill
  • Wednesday- Existing building steel exploration- Minor noise & vibration