June 5 – June 8

View construction map [PD.F]

WORK AREA “A”- Science and Engineering Courtyard (North)

  • Monday: Install supplemental steel on Existing columns- Potential minor vibration and noise
  • Monday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Tuesday: Install supplemental steel on Existing columns- Potential minor vibration and noise
  • Tuesday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Tuesday: Foundation excavation of “NEW EDITION”- Increased Truck traffic during operation
  • Wednesday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Wednesday: Foundation excavation of “NEW EDITION”- Increased Truck traffic during operation
  • Thursday: Remove existing waterproofing from foundations “NEW EDITION”; Potential minor vibration and noise
  • Thursday: Foundation excavation of “NEW EDITION”- Increased Truck traffic during operation

WORK AREA “B”- South side of Science and Engineering

  • Monday; Place rebar and Formwork for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
  • Monday; Waterproofing abatement/ pipe removal SW corner foundation (Line L-Q/0.9)
  • Tuesday; Place concrete for foundations SE corner (Lines 00-0.0/C-D) Truck traffic/ concrete pumps/Flag-persons provided
  • Tuesday; Waterproofing abatement/ pipe removal SW corner foundation (Line L-Q/0.9)
  • Wednesday; Place rebar for foundation walls SE corner (Lines 00-0.9/C-D)- Potential minor vibration and noise
  • Wednesday; Foundation excavation of SW corner (Lines L-Q/0-0.9)- Truck Traffic, flag persons provided
  • Thursday; Place rebar for foundation walls SE corner (Lines 00-0.9/C-D)- Potential minor vibration and noise
  • Thursday; Foundation excavation of SW corner (Lines L-Q/0-0.9)- Truck Traffic, flag persons provided

WORK AREA “C”- Alexander Lane

  • Thursday- Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7 a.m.- 5 p.m .

Temporary Sheeting Installation, Thursday, June 1

View construction map [PD.F]

Starting Thursday morning temporary sheeting installation operations shall continue along the South West Corner of the existing Science & Engineering building. The crane and sheeting shall be mobilized to this area on Thursday morning and actual work is scheduled to begin on Thursday at 9:00 a.m.

Please expect minor vibration and noise during activity.  Student and faculty shall be directed to walk through Wold, Science & Engineering, and exit at Bailey to Gain access to the Alumni Gym. Flag persons shall be available to direct student and faculty traffic during this time. The operation is anticipated to be completed Thursday, June 1 by 11:30 a.m.

May 26 – June 1

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)

  • Friday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50pm
  • Tuesday: Remove existing waterproofing from foundations -Potential minor vibration & noise
  • Wednesday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50pm
  • Wednesday: Remove existing waterproofing from foundations -Potential minor vibration & noise
  • Wednesday: Install supplemental steel on Existing columns- work start dependent on paint removal/ Potential minor vibration & noise
  • Wednesday: Potential Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise
  • Thursday: Anticipate Remove existing waterproofing from foundations “NEW EDITION”; Potential minor vibration & noise
  • Thursday: Potential Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise
  • Thursday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 11:30am

WORK AREA “B”- South side of Science & Engineering

  • Friday; Excavate Foundations SE corner S&E (Lines E-C/00-01)- Truck traffic, flag-persons provided
  • Friday: Remove existing water line/ Backfill -Truck traffic, flag-persons provided
  • Tuesday: Backfill waterline- Truck traffic, flag-persons provided
  • Tuesday: Waterproofing abatement/ pipe removal SE corner foundation
  • Wednesday:  Complete Foundation Excavation SE corner of S&E- Sidewalk closed Relocate students/faculty to new asphalt walkway during operations
  • Wednesday: Form concrete foundations- Sidewalk closed Relocate students/faculty to new asphalt walkway during operations
  • Wednesday: Potential Install Temporary Sheeting for SW Corner- Potential minor vibration & noise

WORK AREA “C”- Alexander Lane

  • Thursday- Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7am-3pm