View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)
- Thursday: Place geotextile fabric and 6-inches of compacted sub-base/ Establish survey points for “NEW EDITION”- Potential Minor Vibration & Noise
- Friday: Continue survey points for “NEW EDITION”; Start excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise
- Monday: Continue excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise
- Tuesday: Layout concrete removal on existing columns (North side of S&E)
- Wednesday: Remove concrete from existing columns- Vibration & Noise to adjacent classrooms North side of S&E
WORK AREA “B”- South side of Science & Engineering
- Friday: Relocate existing condenser units- Coordinate with facility IT department during operation
- Monday: Remove existing tree (morning) & begin utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations
- Tuesday: Continue utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations
- Wednesday: Continue utility relocations SW corner S&E.- Relocate students/faculty to new asphalt walkway during operations
WORK AREA “C”- Alexander lane
- Thursday through Monday; Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7 a.m.- 3 p.m.
WORK AREA “D”- Contractor break Area
- Friday: Install temporary fence & gates
WORK AREA “E”- Contractor Material Lay-down Area
- Thursday: Remove curb, box out & asphalt paving to widen entrance at Alexander Drive- Flag-persons provided at each portion of each portion of intersection
- Friday: Install temporary fence