January 15 – January 19, 2018

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: MEP Rough in Basement level
  • Monday: Apply Spray on fireproofing in basement (Level 1)
  • Monday: Install metal stud wall frame (Level 1)
  • Monday: MEP rough In Level 1
  • Monday: Install temporary enclosures along 7 Lines (Existing S&E)
  • Monday: Prep Level 2 east deck for concrete placement
  • Monday: Installation of curtain wall clips
  • Tuesday: Steel Detail work(New Addition)
  • Tuesday: Install temporary building enclosure Level 3
  • Tuesday: Prep Level 2 east deck for concrete placement
  • Tuesday: installation of CMU walls (basement new addition)
  • Tuesday: MEP rough in Basement of new addition
  • Tuesday: Grout steel column bases (Level 1)
  • Tuesday: Apply SOFP level 1 new addition
  • Tuesday: Install metal stud wall frame (Level 1)
  • Tuesday: MEP rough In Level 1
  • Tuesday: Installation of curtain wall clips
  • Wednesday: Place Concrete Level 2 East- MILESTONE
  • Wednesday: Apply SOFP on level 1
  • Wednesday: MEP rough in Basement of new addition
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: Install metal stud wall frame (Level 1)
  • Wednesday: MEP rough In Level 1
  • Wednesday: Install temporary building enclosure Level 3
  • Wednesday: Installation of curtain wall clips
  • Thursday: MEP rough In Level 1
  • Thursday: MEP rough in Basement of new addition
  • Thursday: Installation of CMU walls (basement new addition)
  • Thursday: Apply SOFP level 1 East steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in Basement of new addition

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Selective demolition & removals Level 1 through Level 3
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE

January 8 – January 12, 2018

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: MEP Rough in Basement level
  • Monday: Apply Spray on fireproofing in basement (Level 0)
  • Monday: Install underground duct bank between Steinmetz & Butterfield
  • Monday: Backfill Generator Pad located between Steinmetz & Butterfield
  • Tuesday: Complete Steel Erection & Detail (New Addition); MILESTONE
  • Tuesday: Install temporary building enclosure Level 2
  • Tuesday: Install MEP sleeves & boxes Level 2 East
  • Tuesday: installation of CMU walls (basement new addition)
  • Tuesday: MEP rough in Basement of new addition
  • Tuesday: Grout steel column bases (Level 1)
  • Tuesday: Apply SOFP level 0 & level 1 new addition
  • Tuesday: Install underground duct bank between Steinmetz & Butterfield
  • Tuesday: Place level 0 housekeeping pads
  • Wednesday: Place Concrete underground duct bank between Steinmetz & Butterfield
  • Wednesday: Apply SOFP on level 1
  • Wednesday: MEP rough in Basement of new addition
  • Wednesday: installation of CMU walls (basement new addition)
  • Thursday: Place concrete L2 SOD West MILESTONE
  • Thursday: Prep for Level 2 EAST SOD concrete placement
  • Thursday: MEP rough in Basement of new addition
  • Thursday: Installation of CMU walls (basement new addition)
  • Thursday: Apply SOFP level 1 WEST steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in Basement of new addition
  • Friday: Apply SOFP level 1 WEST steel beams
  • Friday: Prep level 2 east SOD placement

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Selective demolition & removals Level 1 through Level 3
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Thursday: Place Concrete SOD SW IT vault- MILESTONE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE

December 25 – December 29

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Tuesday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION &
    NOISE
  • Tuesday: Installation CMU walls (basement new addition)
  • Tuesday: MEP Rough in Basement level
  • Tuesday: Install temporary building enclosure Level 1 & 2
  • Tuesday: Place spray-on fireproofing in basement (Level 0)
  • Tuesday: Excavate underground duct bank between Steinmetz & Butterfield
  • Tuesday: Backfill Generator Pad located between Steinmetz & Butterfield
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Install temporary building enclosure Level 1 & 2
  • Wednesday: Install MEP sleeves & boxes Level 2 East
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: MEP rough-in Basement of new addition
  • Wednesday: Install underground duct bank between Steinmetz & Butterfield
  • Wednesday: Apply SOFP on level 0
  • Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: MEP rough-in Basement of new addition
  • Thursday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: installation of CMU walls (basement new addition)
  • Thursday: Place concrete L2 SOD West
  • Thursday: Prep for Level 2 EAST SOD concrete placement
  • Thursday: Apply SOFP basement level steel beams
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Apply SOFP basement level 1 WEST steel beams
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough-in Basement of new addition

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Existing Elevator removal
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Existing Elevator removal
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Thursday: Existing Elevator removal
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Existing Elevator removal