December 18 – December 22, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel erection and detail work (new addition); expect minor vibration and noise
  • Monday: Installation CMU walls (basement new addition)</li
  • Monday: Backfill electrical conduit & Excavate for electrical room conduit
  • Monday: Install mechanical sleeves and floor boxes for level 1 deck
  • Monday: Install underground duct bank between Steinmetz & Butterfield
  • Tuesday: Steel erection and detail work (new addition) expect minor vibration and noise
  • Tuesday: prep for SOG concrete placement for MEP’s & electrical rooms
  • Tuesday: MEP rough in basement of new addition
  • Tuesday: Install mechanical sleeves and floor boxes for level 1 deck
  • Tuesday: Installation of CMU walls (basement new addition)
  • Tuesday: Install underground duct bank between Steinmetz & Butterfield
  • Wednesday: Steel erection and detail (new addition); expect minor vibration and noise
  • Wednesday: Place concrete SOG for the new addition (basement level)
  • Wednesday: Prep level 1 deck for concrete placement
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: MEP rough in basement of new addition
  • Wednesday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: Steel erection and detail (new addition); expect minor vibration and noise
  • Thursday: MEP rough in basement of new addition
  • Thursday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: installation of CMU walls (basement new addition)
  • Thursday: Prep for level 1 SOD concrete placement
  • Friday: Steel erection and detail new addition; expect minor vibration and noise
  • Friday: level 1 SOD concrete placement
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in basement of new addition
  • Saturday: Steel erection and detail new addition; expect minor vibration and noise

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Tuesday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Tuesday: Existing elevator removal
  • Wednesday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Wednesday: Existing elevator removal
  • Thursday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Thursday: Existing Elevator removal
  • Friday: Selective demolition & removals level 1 through 3; expect minor vibration and noise
  • Friday: Existing elevator removal

December 11 – December 16, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Installation CMU walls (basement new addition)
  • Monday: Backfill electrical conduit & Excavate for electrical room conduit
  • Monday: Install mechanical Sleeves & floor boxes for level 1 deck
  • Monday: Install underground duct bank between Steinmetz & Butterfield
  • Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: prep for SOG concrete placement for MEP’s & Electrical rooms
  • Tuesday: MEP rough in Basement of new addition
  • Tuesday: Install mechanical Sleeves & floor boxes for level 1 deck
  • Tuesday: Installation of CMU walls (basement new addition)
  • Tuesday: Install underground duct bank between Steinmetz & Butterfield
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Place concrete SOG for the new addition (basement level)
  • Wednesday: Prep level 1 deck for concrete placement
  • Wednesday: installation of CMU walls (basement new addition)
  • Wednesday: MEP rough in Basement of new addition
  • Wednesday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: MEP rough in Basement of new addition
  • Thursday: Install underground duct bank between Steinmetz & Butterfield
  • Thursday: installation of CMU walls (basement new addition)
  • Thursday: Prep for Level 1 SOD concrete placement
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Level 1 SOD concrete placement
  • Friday: installation of CMU walls (basement new addition)
  • Friday: MEP rough in Basement of new addition
  • Saturday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Existing Elevator removal
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Existing Elevator removal
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Thursday: Existing Elevator removal
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Existing Elevator removal

December 4 – December 9, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection & Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: installation of dowels for CMU walls (basement new addition)
  • Monday: Backfill electrical conduit & Excavate for electrical room conduit
  • Monday: Excavate for underground duct bank between Steinmetz & Butterfield
  • Tuesday: Steel Erection & Detail work (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill electrical conduit & Excavate for electrical room conduit
  • Tuesday: Waterproofing Abatement (Basement doors New addition)
  • Tuesday: Installation of CMU walls (basement new addition)
  • Wednesday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Backfill electrical conduit & Excavate for electrical room conduit
  • Wednesday: Waterproofing Abatement (Basement doors New Addition)
  • Wednesday: installation of CMU walls (basement new addition)
  • Thursday: Steel Erection & Detail (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Thursday: Backfill electrical conduit & Excavate for electrical room conduit
  • Thursday: Waterproofing Abatement (Basement doors New addition)
  • Thursday: installation of CMU walls (basement new addition)
  • Friday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Backfill electrical conduit & Excavate for electrical room conduit
  • Friday: installation of CMU walls (basement new addition)
  • Friday: Waterproofing Abatement (Basement doors New addition)
  • Saturday: Steel Erection & Detail New Addition; EXPECT MINOR VIBRATION & NOISE

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Monday: Existing utility enabling
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Existing utility enabling
  • Wednesday: Existing Utility Enabling
  • Thursday: Existing Utility Enabling
  • Friday: Existing Utility Enabling