November 5 – November 10, 2017

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Steel Erection sequence 2A (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Monday: Basement MEP excavation and installation; Expect truck traffic and minor noise
  • Monday: Installation of floor slab electric conduit
  • Tuesday: Basement MEP excavation and installation
  • Tuesday: Steel Erection sequence 2A (New Addition) EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Installation of floor slab electric conduit
  • Tuesday: Install electrical manholes located between Butterfield & Steinmetz
  • Wednesday: Steel Erection sequence 2A (New Addition); EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Basement MEP excavation and installation
  • Wednesday: Install electrical manholes located between Butterfield & Steinmetz
  • Wednesday: Basement Slab on Grade preparation
  • Wednesday: Installation of floor slab electric conduit
  • Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Basement Slab on Grade preparation
  • Thursday: Basement MEP excavation and installation
  • Friday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE
  • Friday: Basement MEP excavation and installation
  • Friday: Installation of floor slab electric conduit
  • Friday: Basement Slab on Grade preparation

WORK AREA “B”- South side of Science & Engineering

  • Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Tuesday: Exterior Brick & Concrete removal SW corner (Start 1pm)
  • Wednesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Wednesday: Exterior Brick & Concrete removal SW corner (Start 2pm)
  • Thursday: Exterior Brick & Concrete removal SW corner (Start 1pm)
  • Thursday: Relocation condenser units
  • Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
  • Friday: Relocation of condenser units
  • Friday: Exterior Brick & Concrete removal SW corner (Start 1pm); EXPECT NOISE & VIBRATION

October 30 – November 3

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

> Monday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE

> Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)

> Monday: Elevated slab shoring removal

> Monday: Establish emergency egress North side of Bailey hall & relocate fence

> Monday: Excavate & install underground utilities

> Tuesday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE

> Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)

> Tuesday: Excavate & Install underground utilities

> Tuesday: Install electrical manholes located between Butterfield & Steinmetz

> Wednesday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE

> Wednesday: Underground utility excavation

> Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE

> Thursday: Excavate & Install underground utilities

> Thursday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE

> Friday: Steel Erection New Addition; EXPECT MINOR VIBRATION & NOISE

WORK AREA “B”- South side of Science & Engineering

> Monday: Complete all emergency egress asphalt paving & relocate temp. fence

> Tuesday: CLOSE CONNECTOR BETWEEN BAILEY HALL & S&E

> Wednesday: Selective demolition/ enabling/ temp wall installation

> Thursday: Relocation condenser units

> Thursday: Selective demolition/ enabling/ temp wall installation

> Friday: Selective demolition/ enabling/ temp wall installation

> Friday: Relocation of condenser units

Bailey Hall/ S&E re-phase work

> Monday: Remove all excess materials, clean

October 23 – October 27

>>View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install waterproofing membrane New addition foundations
  • Monday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Monday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Monday: Elevated slab shoring removal
  • Tuesday: Install waterproofing membrane New addition foundations
  • Tuesday: Selective demolition on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Tuesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Elevated slab shoring removal
  • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Wednesday: Elevated Slab shoring removal
  • Wednesday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Underground utility excavation
  • Thursday: Elevated slab shoring removal
  • Thursday: Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
  • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Thursday: Underground utility excavation
  • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
  • Friday: Underground Utility excavation
  • Friday: Elevated slab shoring removal

WORK AREA “B”- South side of Science & Engineering

  • Monday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Tuesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Install storm line and backfill;Expect truck traffic and minor noise (flag person will be present)
  • Wednesday: Grade for new asphalt ramp
  • Thursday: Place Asphalt;Expect truck traffic and minor noise (flag person will be present)
  • Friday: re configure temporary fence and open entrance