May 11 – May 18, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)

  • Thursday: Remove Concrete from existing Columns & brick fascia on North side of S&E- Noise Impact, work scheduled to STOP by 1:50pmThursday: Install
  • Temporary Sheeting for “NEW EDITION”; work to start at 3:00pm- Potential Minor Vibration & Noise
  • Friday: Steinmetz Symposium -NO WORK SCHEDULED
  • Monday: Continue concrete removal on existing columns (North side of S&E)- NOISE IMPACT, work scheduled to STOP by 1:50pm
  • Monday: Install Temporary Sheeting for “NEW EDITION”; work start time dependent on Thursday results/ Potential minor vibration & noise
  • Tuesday: Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise
  • Wednesday: Install Temporary Sheeting for “NEW EDITION”- Potential minor vibration & noise

WORK AREA “B”- South side of Science & Engineering

  • Thursday; Insulate condenser lines
  • Thursday; Backfill condenser lines
  • Thursday; Subsurface utility exploration on SW corner of S&E- Relocate students/faculty to new asphalt walkway during operations
  • Friday; Steinmetz Symposium -NO WORK SCHEDULED
  • Monday; Subsurface utility exploration on SW corner of S&E- Relocate students/faculty to new asphalt walkway during operations
  • Monday; Temporary fence installation-

WORK AREA “C”- Alexander Lane

  • Thursday- Increased truck traffic due to deliveries – Flag persons provided during deliveries, North lift gate on Alexander Lane open 7a.m. – 3 p.m.