July 10 – July 15, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Demolition of stair-tower located between Bailey Hall and  Science Engineering – Vibration and noise expected, Spotters provided
  • Monday: Shut down fan in Room S003 servicing Vivarium rooms, start fan relocation
  • Monday: Install Form-work/Rebar for foundations RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Monday: Exterior waterproofing removal on existing foundation R2/RH
  • Monday: Tie in Exhaust/Intake duct work S003
  • Tuesday: Place Concrete for foundations RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Tuesday: Demolition of stair-tower located between Bailey Hall and Science Engineering- Vibration and noise expected, Spotters provided
  • Tuesday: Tie in Exhaust/Intake duct work S003
  • Wednesday: Foundation excavation of RH/ R8-R18- Increased Truck traffic during operationv
  • Wednesday: Strip form-work RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Wednesday: Continue Backfill & Plumbing installation
  • Wednesday: Complete Intake/Exhaust installation S003; Turn system back on
  • Wednesday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided
  • Thursday: Install Form-work/Rebar for foundations RH/R8-R18
  • Thursday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided
  • Thursday: Continue Backfill & Plumbing installation
  • Friday: Install Form-work/Rebar for foundations RH/R8-R18, walls R4-R8
  • Friday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided

WORK AREA “B”- South side of Science & Engineering

  • Monday; Excavate for Foundations S-Q/ 0-0.9
  • Monday; Re-configure temporary fence
  • Tuesday; Complete excavation SW corner (Lines 0.00-0.9/S-Q)- Truck Traffic, minor noise, flag-persons provided
  • Wednesday; Install Form-work/Rebar for foundations corner (Lines 00-0.0/L-Q)- Truck traffic, flag-persons provided
  • Thursday; Place concrete footings SW S&E; Lines 0.00-0.9/ L-Q- Truck Traffic, minor noise, flag-persons provided
  • Friday; strip Form-work for foundations corner (Lines 00-0.0/L-Q)- Truck traffic, flag-persons provided