WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Monday: Installation CMU walls (basement new addition)
- Monday: MEP Rough in Basement & level 1
- Monday: Apply SOFP Level 2
- Monday: layout metal stud wall frame (Level 1 East)
- Monday: Install temporary enclosures level 4 (Existing S&E)
- Monday: Install storm lines on Level 2
- Monday: Install MEP sleeves/Hangers on Level 4
- Monday: Installation of curtain wall clips
- Monday: Installation of exterior wall clips
- Tuesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Tuesday: Install temporary enclosures level 4(Existing S&E)
- Tuesday: Install storm lines on Level 2
- Tuesday: Installation of CMU walls (basement new addition)
- Tuesday: MEP rough in Basement & level 1
- Tuesday: Start Apply SOFP level 2
- Tuesday: Layout metal stud wall frame (Level 1East)
- Tuesday: Installation of curtain wall clips
- Tuesday: Complete MEP sleeves/Hangers on Level 4
- Wednesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Wednesday: Complete Rebar Level 4
- Wednesday: Apply SOFP on level 2 East
- Wednesday: MEP rough in Basement & Level 1
- Wednesday: installation of CMU walls (basement new addition)
- Wednesday: Complete temporary building enclosure Level 4
- Wednesday: Installation of curtain wall clips
- Wednesday: Install MEP sleeves on Level 4
- Thursday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Thursday: Prep for concrete placement Level 4 Roof
- Thursday: MEP rough In Basement & Level 1
- Thursday: Installation of CMU walls (basement new addition)
- Thursday: Complete SOFP level 2 – MILESTONE
- Thursday: Start level 2 MEP Rough in (WEST)
- Thursday: Installation of exterior wall clips
- Friday: Complete installation of CMU walls (basement new addition)- MILESTONE
- Friday: MEP rough in Basement, Level 1, & Level 2
- Friday: Apply SOFP level 3 WEST & EAST steel beams
- Friday: Level 4 (LOW ROOF) Concrete placement- MILESTONE
- Friday: Installation of curtain wall clips
- Friday: Installation of exterior wall clips
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Wednesday: Selective demolition & removals Level 1 through Level 3
- Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE