September 25 – September 29, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Install elevated deck form work
  • Monday: Install Rebar & form-work for remaining foundations
  • Monday: Excavate and backfill -expect trucks and minor noise, flag persons shall be provided
  • Monday: Install foundation waterproofing
  • Monday: Install mechanical sleeves & hangers on elevated deckv
  • Monday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Tuesday: Install elevated deck form work
  • Tuesday: Place concrete fin New addition foundations-expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Excavate and backfill -expect trucks and minor noise, flag persons shall be provided
  • Tuesday: Install foundation waterproofing
  • Tuesday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Wednesday: Install elevated deck form work
  • Wednesday: Install form-work & rebar for foundation walls
  • Wednesday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Wednesday: Backfill foundations-expect trucks and minor noise, flag persons shall be provided
  • Thursday: Install elevated deck form work
  • Thursday: Continue installation of steel clips on existing S&E building – minor noise & vibration
  • Thursday: Install form-work & rebar for foundation walls
  • Friday: Install elevated deck form work
  • Friday: Place concrete for foundations-expect trucks and minor noise, flag persons shall be provided
  • Saturday: Remove remainder of temporary sheeting

WORK AREA “B”- South side of Science & Engineering

  • Monday- Foundation Waterproofing
  • Tuesday- Foundation backfill
  • Saturday: Remove remainder of temporary sheeting

September 18 – September 22, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

    • Monday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Monday: Strip Concrete walls
    • Monday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Monday: Remove shoring under Level 1 deck
    • Tuesday: Excavate & Backfill in courtyard
    • Tuesday: Install shoring for elevated deck
    • Tuesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Tuesday: Install MEP sleeves in concrete foundation wall
    • Tuesday: Place Concrete walls/Footings; Expect truck traffic and minor noise (flag person will be present)
    • Wednesday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Wednesday: Remove shoring under Level 1 deck
    • Wednesday:Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Wednesday: Install shoring for elevated deck
    • Wednesday: Install Sump Pit in courtyard
    • Wednesday: Temporarily remove exhaust stack on Existing S&E
    • Thursday: Place Concrete walls & Footings; Expect truck traffic and minor noise (flag person will be present)
    • Thursday: Install shoring for elevated deck
    • Thursday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Thursday: Excavate & Backfill in courtyard; Expect truck traffic and minor noise (flag person will be present)
    • Friday: Install shoring for elevated deck
    • Friday: Install steel on existing beams/Columns along S&E; EXPECT MINOR VIBRATION & NOISE
    • Friday: Excavate & Backfill in courtyard Expect truck traffic and minor noise (flag person will be present)

WORK AREA “B”- South side of Science & Engineering

    • Monday: Foundation wall waterproofing
    • Tuesday: Foundation Wall waterproofing
    • Wednesday: Backfill foundation walls (SW) Expect truck traffic and minor noise (flag person will be present)
    • Thursday: Backfill foundation walls (SW) Expect truck traffic and minor noise (flag person will be present)

September 5 – September 8, 2017

View construction map [PD.F]

WORK AREA “A”- Science and Engineering Courtyard (North)/ Existing Building

  • Tuesday: Install solder pile and lagging in courtyard
  • Tuesday: Install rebar/electric conduits/Sleeves/form-work for elevated deck
  • Tuesday: Layout and Install sleeve for electrical and plumbing utilities
  • Tuesday: Selective Removals of existing Science and Engineering Building, levels 1 – 3 noise and vibration expected
  • Wednesday: Excavate and install new sewer pit
  • Wednesday: Layout and Install underground MEP
  • Wednesday: Place concrete foundations in courtyard adjacent to Bailey Hall
  • Wednesday: Install solder pile and lagging in courtyard
  • Wednesday: Saw-cut existing concrete slab in SandE basement noise and vibration expected; coordinate with class schedules”
  • Wednesday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Thursday: Place Concrete for elevated deck- (tentative; Schedule based on College coordination and weather)
  • Thursday: Layout and Install underground MEP
  • Thursday: Install solder pile and lagging in courtyard
  • Thursday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Thursday: Place Concrete for walls in new addition
  • Friday: Layout and Install sleeve for electrical and plumbing utilities
  • Friday: Install solder pile and lagging in courtyard
  • Friday: Demo walkway between Steinmetz and Butterfield (tentative)
  • Friday: Place concrete foundations New Addition
  • Saturday: Excavation/Form-work for concrete foundations

WORK AREA “B”- South side of Science and Engineering

  • Tuesday: Install door in room S006; (coordination with college)
  • Tuesday: Backfill Expect truck traffic and minor noise (flag person will be present)
  • ALL WEEK: Area clean-up

WORK AREA “C” – Alexander Lane

  • Expect continued construction traffic (flagger and spotter provided for all deliveries)