July 10 – July 15, 2017

View construction map [PD.F]

WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building

  • Monday: Demolition of stair-tower located between Bailey Hall and  Science Engineering – Vibration and noise expected, Spotters provided
  • Monday: Shut down fan in Room S003 servicing Vivarium rooms, start fan relocation
  • Monday: Install Form-work/Rebar for foundations RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Monday: Exterior waterproofing removal on existing foundation R2/RH
  • Monday: Tie in Exhaust/Intake duct work S003
  • Tuesday: Place Concrete for foundations RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Tuesday: Demolition of stair-tower located between Bailey Hall and Science Engineering- Vibration and noise expected, Spotters provided
  • Tuesday: Tie in Exhaust/Intake duct work S003
  • Wednesday: Foundation excavation of RH/ R8-R18- Increased Truck traffic during operationv
  • Wednesday: Strip form-work RH/ R4-R8, walls RH/R2-R4, Columns A1 Line
  • Wednesday: Continue Backfill & Plumbing installation
  • Wednesday: Complete Intake/Exhaust installation S003; Turn system back on
  • Wednesday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided
  • Thursday: Install Form-work/Rebar for foundations RH/R8-R18
  • Thursday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided
  • Thursday: Continue Backfill & Plumbing installation
  • Friday: Install Form-work/Rebar for foundations RH/R8-R18, walls R4-R8
  • Friday: Demolition of stair-tower between Bailey hall & Science & Engineering- Vibration and noise expected, Spotters provided

WORK AREA “B”- South side of Science & Engineering

  • Monday; Excavate for Foundations S-Q/ 0-0.9
  • Monday; Re-configure temporary fence
  • Tuesday; Complete excavation SW corner (Lines 0.00-0.9/S-Q)- Truck Traffic, minor noise, flag-persons provided
  • Wednesday; Install Form-work/Rebar for foundations corner (Lines 00-0.0/L-Q)- Truck traffic, flag-persons provided
  • Thursday; Place concrete footings SW S&E; Lines 0.00-0.9/ L-Q- Truck Traffic, minor noise, flag-persons provided
  • Friday; strip Form-work for foundations corner (Lines 00-0.0/L-Q)- Truck traffic, flag-persons provided

Science & Engineering Elevator OUT OF SERVICE Notice

Please be advised that the elevator located between Bailey hall and the existing Science & Engineering Building (Elevator 1) shall be taken out of service starting today at 1 p.m. through tomorrow, June 15, 3 p.m. Please see drawing (link below) that displays alternate walk path to Elevator #2 (S&E) and Wold elevator.

If you should have any questions or concerns please don’t hesitate to contact  jathomas@tcco.com

View drawing of alternative walk path [PD.F]

June 12 – June 15, 2017

View construction map [PD.F]

WORK AREA “A”- Science and Engineering Courtyard (North)

  • Monday: Excavate foundations new addition Lines R1-R6- Increased Truck traffic during operation
  • Monday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Monday: Begin Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Monday: Mechanical, Electrical, Plumbing,  relocation between Bailey Hall and Science and Engineering
  • Tuesday: Excavate foundations  new addition Lines R1-R6- Increased Truck traffic during operation
  • Tuesday: Remove existing waterproofing from foundations -Potential minor vibration and noise
  • Tuesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Tuesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Wednesday: Foundation excavation of “new addition- Increased Truck traffic during operation
  • Wednesday: Install form-work new addition; R1-R6
  • Wednesday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Wednesday: Continue Temporary wall work located in Room 014 (Existing Science and Engineering)
  • Wednesday: Start Temporary wall work located in room S201, S201A, S205
  • Thursday: Mechanical, Electrical, Plumbing relocation between Bailey Hall and Science and Engineering
  • Thursday: Install Rebar new addition; R1-R6
  • Thursday: Temporary wall work located in room S201, S201A, S205 (Level 2 SandE)

WORK AREA “B”- South side of Science and Engineering

  • Monday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
  • Tuesday: Place rebar and Form-work for foundations SE corner (Lines 00-0.0/C-D)- Truck traffic, flag-persons provided
  • Tuesday: Install additional shoring SW foundations (S-Q/ 0.00-0.9)
  • Wednesday: Place concrete for foundation walls SE corner (Lines 00-0.9/C-D)- Potential minor vibration and noise
  • Wednesday: Foundation undercut/stone install of SW corner (Lines S-Q/0-0.9)- Truck Traffic, flag persons provided
  • Thursday: Waterproofing abatement SW corner (S-Q/0-0.9) Potential minor vibration and noise
  • Remove form-work: Foundation walls SE corner (Lines 00-0.9/C-D)- Truck Traffic, flag persons provided