WORK AREA “A”- Science and Engineering Courtyard (North)/ Existing Building
- Monday: Excavation of stair-tower foundation located between Bailey Halland Science Engineering- Vibration and noise expected, Spotters provided
- Monday: Excavate and install form-work for foundations located in new addition
- Monday: Strip form-work from foundations “new additions”
- Tuesday: Excavation of stair-tower foundation located between Bailey Halland Science Engineering- Vibration and noise expected, Spotters provided
- Tuesday: Excavate and install form-work for foundations located in new addition
- Tuesday: Install underground plumbing new addition
- Tuesday: Abate existing foundation waterproofing at Bailey Hall stairwell foundation
- Wednesday: Demolition walkway between Steinmetzand Butterfield halls- Vibration and noise expected, Spotters provided
- Wednesday: Excavate and install form-work for foundations located in new addition
- Wednesday: Install underground plumbing and electric new addition
- Thursday: install form-work/Rebar for foundations located in new addition
- Thursday: Foundation Excavation in new addition
- Thursday: Demolition walkway between Steinmetzand Butterfield halls- Vibrationand noise expected, Spotters provided
- Thursday: Install underground plumbing and electric
- Friday: Place Concrete foundations new addition
- Friday: Backfill, Underground Plumbing and electrical installation new addition
WORK AREA “B”- South side of Science and Engineering
- Monday; Waterproofing Abatement -Truck Traffic, minor noise, flag-persons provided
- Tuesday; Waterproofing Abatement- Truck Traffic, minor noise, flag-persons provided
- Wednesday; Remove Existing steel supports- Spotters provided for truck deliveries