WORK AREA “A”- Science and Engineering Courtyard (North)/ Existing Building
- Tuesday: Install solder pile and lagging in courtyard
- Tuesday: Install rebar/electric conduits/Sleeves/form-work for elevated deck
- Tuesday: Layout and Install sleeve for electrical and plumbing utilities
- Tuesday: Selective Removals of existing Science and Engineering Building, levels 1 – 3 noise and vibration expected
- Wednesday: Excavate and install new sewer pit
- Wednesday: Layout and Install underground MEP
- Wednesday: Place concrete foundations in courtyard adjacent to Bailey Hall
- Wednesday: Install solder pile and lagging in courtyard
- Wednesday: Saw-cut existing concrete slab in SandE basement noise and vibration expected; coordinate with class schedules”
- Wednesday: Demo walkway between Steinmetz and Butterfield (tentative)
- Thursday: Place Concrete for elevated deck- (tentative; Schedule based on College coordination and weather)
- Thursday: Layout and Install underground MEP
- Thursday: Install solder pile and lagging in courtyard
- Thursday: Demo walkway between Steinmetz and Butterfield (tentative)
- Thursday: Place Concrete for walls in new addition
- Friday: Layout and Install sleeve for electrical and plumbing utilities
- Friday: Install solder pile and lagging in courtyard
- Friday: Demo walkway between Steinmetz and Butterfield (tentative)
- Friday: Place concrete foundations New Addition
- Saturday: Excavation/Form-work for concrete foundations
WORK AREA “B”- South side of Science and Engineering
- Tuesday: Install door in room S006; (coordination with college)
- Tuesday: Backfill Expect truck traffic and minor noise (flag person will be present)
- ALL WEEK: Area clean-up
WORK AREA “C” – Alexander Lane
- Expect continued construction traffic (flagger and spotter provided for all deliveries)