>>View construction map [PD.F]
WORK AREA “A”- Science & Engineering Courtyard (North)/ Existing Building
- Monday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Monday: Installation CMU walls (basement new addition)
- Monday: MEP Rough in Basement & level 1
- Monday: Complete Spray on fireproofing on Steel Level 1 “7” line- MILESTONE
- Monday:layout metal stud wall frame (Level 2)
- Monday: Install temporary enclosures level 4 (Existing S&E)
- Monday: Install MEP sleeves on Level 3 “7” line
- Monday: Install MEP sleeves/Hangers on Level 4
- Monday: Installation of curtain wall clips
- Tuesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Tuesday: Install temporary enclosures level 4(Existing S&E)
- Tuesday: Install MEP sleeves on Level 3 “7” line
- Tuesday: installation of CMU walls (basement new addition)
- Tuesday: MEP rough in Basement & level 1
- Tuesday: Start Apply SOFP level 2 West new addition
- Tuesday: Layout metal stud wall frame (Level 2 East)
- Tuesday: Installation of curtain wall clips
- Tuesday: Install MEP sleeves/Hangers on Level 4
- Wednesday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Wednesday: Install Rebar Level 3 “7” line deck
- Wednesday: Apply SOFP on level 2 West
- Wednesday: MEP rough in Basement & Level 1
- Wednesday: installation of CMU walls (basement new addition)
- Wednesday: Install temporary building enclosure Level 4
- Wednesday: Installation of curtain wall clips
- Wednesday: Install MEP sleeves on Level 4
- Thursday: Steel Detail work (New Addition); EXPECT MINOR VIBRATION & NOISE
- Thursday: Install Rebar Level 4 West
- Thursday: MEP rough In Basement & Level 1
- Thursday: Installation of CMU walls (basement new addition)
- Thursday: Apply SOFP level 2 West steel beams
- Thursday: Install MEP sleeves on Level 4
- Thursday: Install temporary building enclosure Level 4
- Friday: installation of CMU walls (basement new addition)
- Friday: MEP rough in Basement & Level 1
- Friday: Apply SOFP level 2 WEST & EAST steel beams
- Friday: Level 3 (7-Line) & level 2 (7-Line) Concrete placement- MILESTONE
- Friday: Install temporary building enclosure Level 4
- Friday: Install MEP sleeves on Level 4
WORK AREA “B”- South side of Science & Engineering
- Monday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Tuesday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Wednesday: Selective demolition & removals Level 1 through Level 3
- Thursday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE
- Friday: Selective demolition & removals Level 1 through 3; EXPECT MINOR NOISE